You are here: GSI Wiki>FRS Web>S2VTPC22 (2026-10-30, NisanYaprakBenal)

S2 — VTPC22 (GTS3EG7T)

FRS Home Page - Areas.gif – S2 – Pictures – Drawings – Cable Connections – TPC Electronics – Memo for preparation before beam time

Official Manual of TPC ( pdf.gif PDF )
Recent Log and Memo about TPC (2019) (External link)

Present Configuration (as of 2020/Oct/22)

  • in a box (pocket) for the S2 vacuum chamber (GTS3EG7T)
  • Window = 100 um Stainless steel (each of front and behind)
  • Gap = 8 cm (drift HV = -3200 V)
  • Normal orientation
  • Now calibration positions should be x = -12, 0, +12 mm and y = -6, 0, +6 mm
  • To have consistent track from all 4 TPCs, one could add the values on page 5 of this memo to the grid position
  • Maximum allowed HV: -3200 V (drift), +1100 V (anode), -700 V (calibration, PMT).
  • For heavy ions, anode and PMT voltages should be much lower than the maximum values.

Status during previous beam time

2021/Feb/15-Feb/22 (12C beam, S533/BARB + EXPERT test)
- HV(anode) = +1050V, HV(drift) = -3200V, HV(grid-pmt) = -700V
- Analog raw signal around 150--200 mV. Vth(tpc module) around 45--60 mV
- Calibration file is /d/land4/sec/s533/tpc22_calib_0024.lmd (Logbook p41-43)
- Parameter sets used during experiment is found here.
2020/June/05--June/08 (proton beam, WASA000)
- Applied voltages: anode HV = +1150 V, drift = -3200 V, calib-pmt =
- Calibration file: wasa2020june_tpc22calib_[0015-0018].lmd
2020/May/xx--May/xx (Pb beam, S469, very low evenry)
2020/Apr/08--Apr/27 (Pb beam, S468, S482, S481)
- Applied voltages: anode HV = +580 V, drift HV = -3200V, fiber-PMT = -350V
2020/Feb/28--Mar/16 (Xe beam, S474, S459, S480)
- Applied voltages: anode HV = +600 V, drift HV = -3200V, fiber-PMT = -350V
- Used very short time to get the first impression about the beam poisition. Calibration grid (run0114). Parameters
- There are files with all TPC21+22+23+24, which can be used for overall check.
2020/Feb/20--Feb/26 (Kr beam, Ca fragments, Cave-C S467)
- Applied voltages: anode HV = +700 V, drift HV = -3200V.
- Used very short time to get the first impression about the beam poisition. No grid caliberation was performed.
- There are files with all TPC21+22+23+24, which can be used for calibration (if needed). Runs 92--95.
2019/Dec/09--Dec/19 (U beam)
- After changing primary beam from 40Ar to 238U.
- Applied voltages: anode HV = +550 V, drift = -3200V
2019/Nov/18--Dec/06 (Ar beam)
- Installed at S2 as TPC22.
- All signals were checked and ok, calibration scintllator double peak ?? >> to be investigated.
- Gap is 8cm. normal orientation. DL1 signal is fine (see comment in 2019-April run).
- Applied voltages: anode HV = +800 V, drift = -3200V, fiber PMT = -500V.
2019/April/1--3 (107Ag, 290MeV/u, primary beam)
- Installed at S2 as TPC21.
- Signal of TPC22-DL1 is abnormally small. Swapping cables did not work. Something in the TPC chamber should be the reason.
- Other signals are reasonable.
- Calibration scintllator was ok.
- normal orientation - We need to open this TPC after the beam time to investigate problems of DL1.

-- NisanYaprakBenal - 2026-10-26

Updated November 07, 2019

 

Messagelog

 

-- SagarRoy - 2021-06-26
I Attachment Action Size Date Who Comment
Areas.gifgif Areas.gif manage 1 K 2021-07-10 - 11:22 SagarRoy  
pdf.gifgif pdf.gif manage 128 bytes 2021-07-14 - 20:10 SagarRoy  
tpcmanual.pdfpdf tpcmanual.pdf manage 2 MB 2021-07-14 - 20:11 SagarRoy  
Please login to edit this topic
Topic revision: r6 - 2026-10-30, NisanYaprakBenal
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding GSI Wiki? Send feedback | Legal notice | Privacy Policy (german)